Unitized vs Stick Built Curtain Wall

The question every facade specifier faces: factory-built modules or site-assembled grid? This guide compares both systems on the nine criteria that decide real projects — with honest numbers from our engineering team.

Crossover Height: 50–60 m 9-Criteria Comparison Honed by 30 Years of Facades
The Core Difference

Factory modules vs site assembly

Unitized curtain wall

Full floor-height modules — framing, glass, spandrels, gaskets and seals — are assembled in the factory, pressure-tested in batches, then transported and crane-lifted into position. The module arrives as a closed, already sealed element; site crews only connect and gasket the joints between modules.

Stick built curtain wall

Mullions are anchored to the slab, transoms span between them, and glass or panels are glazed in on site. Every step — alignment, drainage, sealing — happens in the open air. It is the traditional method, and for the right building it remains the smartest value play.

Unitized system details →  |  Stick built system details →

Head-to-Head

Nine criteria compared

Criterion Unitized Stick Built Winner
Erection speed8–15 m²/day/crane3–5 m²/day/teamUnitized
Tooling / setup costHigh (design, jigs, lift)LowStick built
Unit cost per m²HigherLower baselineStick built
Quality control pointFactory, batch-testedOn site, crew-dependentUnitized
Weather exposure during buildClosed rain-screen fastOpen grid until sealedUnitized
Geometry flexibilityModule grid constraintsSite-adjustableStick built
Seismic / inter-storey driftRotational joints absorb driftNeeds engineered slip jointsUnitized
Logistics & site constraintsNeeds crane + storageWorks with skylifts, tight sitesStick built
Best height range> 50–60 m towers≤ 50–60 m mid-riseDepends on height
Economics

The 50–60 m crossover explained

Below the crossover height, stick built wins on total cost: no tooling, no crane, simpler logistics. Above it, wind loads rise, erection time dominates the critical path, and the unitized advantage in speed and closed-layer QC shrinks or reverses the cost gap.

The crossover is not a fixed number — it moves with facade area, floor plate, site access, local labor rates and program. That is why Hanart models both options in early-stage cost studies rather than applying rules blindly.

Run the interactive selector to see which fits your project →

Unitized curtain wall modules lifted by crane beside a stick built facade under site assembly
Hybrid Strategy

When to mix both systems

Tower + podium

Unitized modules on the tower for speed and QC; stick built on the podium where geometry changes floor by floor and budgets are tighter.

Corners & transitions

Special corner or parapet zones often switch to stick built detailing because module grids cannot economically follow complex folds.

Interface engineering

Mixing works only with careful interface detailing — thermal, movement, sealant and tolerance continuity between the two systems are designed together, not improvised on site.

See how our engineering team manages hybrid facades →

FAQ

Unitized vs stick built questions, answered

Unitized curtain walls are pre-assembled in factory as full floor-height modules and crane-lifted into place, closed already sealed. Stick built systems are assembled on site from mullions, transoms and infill panels. The difference drives cost, program, QC and weather exposure during erection.

Unitized has a higher unit cost due to tooling, module fabrication and crane logistics, but it is faster to install. On tall towers the schedule saving usually outweighs the premium; on mid-rise buildings stick built is typically the lower total-cost solution.

As a rule of thumb, 50–60 m is the crossover. Below it, stick built is usually cheaper. Above it, the speed, QC and weather-tightness of unitized modules make them competitive or cheaper on total cost and program.

Quality depends on the contractor, not just the system. Unitized moves quality control into the factory with sealed test units; stick built depends on disciplined site assembly and sealing. Both can and must pass the same mock-up air, water and structural tests.

Yes, and it is common: unitized for the tower, stick built for the podium, or unitized for rainscreen-heavy zones and stick built for irregular corners. Interface detailing between the two systems is the key engineering task.